Sr No. |
ECG Makers Made in MODEL- HYBRID-U TYPE
|
MAKER A S.Korea HYBRID-UTYPE
|
MAKER B Europe HYBRID-UTYPE
|
MAKER C USA-China HYBRID U-TYPE
|
|
Exhaust Gas Mass Flow Kg/Hr - % MCR |
123,500 80% MCR
|
134,400 75% MCR
|
123,321 80%MCR
|
1 |
Performance SOx/CO2 ratio - SOx ppm |
4.3/0.1 |
4.3/0.1 |
4.3/0.1 |
2 |
Delivery time from Order - Ex Works |
8 MONTHS |
12 MONTHS |
7 MONTHS |
3 |
Price in US Dollars |
1,950,000.00 |
1,817,950.00 |
1,915,000.00 |
4 |
Payment Terms & Installments |
20/70/10 % |
25/35/35/5 % |
35/25/30/10 % |
5 |
Warranty Period after Delivery |
18 Months |
12 Months |
18 Months |
6 |
Install Time @ YARD/Commissioning @ SEA |
21/25 |
21/15 |
21/21 |
7 |
Scrubber Installation design |
Inside Modified Funnel Casing |
Inside Modified Funnel Casing |
Outside Funnel with external casing |
8 |
Dimensions Dia x H or L x B x H |
3.45x8.90 x5.45m |
4.1 x 10.5m |
3.4x3.1x8.5m(8.8m2) |
9 |
Prefabricated components by OEM |
Scrubber Tower |
Scrubber Tower |
Scrubber Tower sand Outer Casing |
|
DESIGN CRITERIA |
9.6 MW |
9.6 MW |
9.6 MW |
10 |
Power Consumption Open/Closed Kw |
218/422 |
150/200 |
181/184 |
11 |
Back Pressure drop across EGCS |
150 mmAq |
150 mmAq |
150 mm Aq |
12 |
Auxiliary Boiler |
Included |
Included |
Included |
13 |
Low Alkalinity Operations/Closed Loop |
NaOH dosing |
NaOH dosing |
NaOH dosing |
14 |
NaOH (50%) consumption |
400 litres/Hr |
100 litres/MT |
100 litres/MT |
15 |
F.W. Consumption for NaOH dosing |
50 Litres/MWh |
50 Litres/MWh |
50 Litres/MWh |
16 |
Sludge Fomation |
8.5 Kg/hr |
2.8 Kg/hr |
2 Litres/MT HFO |
17 |
Wash Water
Cleaning Capacity |
10.0 m3/hr |
3.9m3 |
15.8
m3 |
18 |
Sea Water
Wash Open Mode |
1000 m3/hr |
1000 m3/hr |
850 m3/hr |
19 |
Make up
Wash Water Closed mode |
10 m3/hr |
10 m3/hr |
10 m3/hr |
20 |
Effluent/Water Monitoring |
Maker A |
Third Party |
Third Party |
21 |
Exhaust gas
Monitoring |
Maker A |
Tritech |
Tritech |
22 |
Water
Treatment System w/Tank |
10 m3/hr |
0.7 m3 x 2 |
13.3 m3 |
23 |
Sea
Water Pumps with VSD m3/h |
3 x
500 m3/hr |
3 x 575
m3/hr |
2 x 450
m3/h |
|
INSTALLATION SUPPORT |
|
|
|
24 |
Basic &
Detailed Design Engineering |
30,000.00 |
30,000.00 |
30,000.00 |
25 |
Commissioning 2x Serv eng x 10 days |
20,000.00 |
20,000.00 |
20,000.00 |
26 |
Documentation & Plan Approval |
15,000.00 |
15,000.00 |
15,000.00 |
|
INSTALLATION YARD / OWNER SUPPLY |
|
|
|
27 |
3 D
Scanning/Preliminary Specifcation |
Owner/Tritech |
Owner/Tritech |
Owner/Tritech |
28 |
Scrubber
Assembly and Erection |
Yard |
Yard |
Yard |
29 |
Installation
Supervision |
Owner |
Owner |
Owner |
30 |
Scrubber
Insulation and Cladding |
Yard |
Yard |
Not
required |
31 |
Funnel
Casing Modification / New |
Yard |
Yard |
Not
required |
32 |
Process /
Wash Water Tank |
30 m3 |
6 m3
x 1 |
13.3 m3 |
33 |
Process
Water Holding Tank |
180 m3 Aft
Pk Tk |
Not
required |
After Peak
Tank |
34 |
Cleaning
Tank In Cleaning Unit |
60 m3 |
3m3 x 2 |
3 m3 x 2 |
35 |
NaOH Dosing
Tank |
15 m3 |
15 m3 |
15 m3 |
36 |
Sludge Tank
/ Portable IBC Totes |
2 m3 |
IBC Totes
2x1m3 |
IBC Totes
3x1m3 |